This paper assesses the connection of a large wind farm to a regional power system with a weak link to the main transmission grid. The study demonstrates that utilization of modern wind turbine technology and automatic generation control schemes allow operation of large wind farms in weak grids. In the case study considered of a regional power system, the viable wind farm capacity may be increased from 50 to 200 MW.
John Olav Giæver TandeKjetil Uhlen, Cost efficient grid integration of large wind farms, EWEC′2003, 16–19 June 2003, Madrid, Spain.
2.
PalssonM.T.ToftevaagT.UhlenK.Tande, J.O.G., Large-scale Wind Power Integration and Voltage Stability Limits in Regional Networks, 2002IEEE-PES Summer Meeting.
3.
PalssonM.T.ToftevaagT.UhlenK.TandeJ.O.G., Control Concepts to Enable Increased Wind Power Penetration, 2003 IEEE-PES Summer Meeting, 13–18 July 2003, Toronto, Canada.