An energy storage plant of 20 MW nominal capacity with pure air exhaust and a recovery ratio in a range up to 72% is described. The principal component requiring development is the regenerator. Tentative cost estimates indicate where the plant may fit in the spectrum of possible storage schemes.
Get full access to this article
View all access options for this article.
References
1.
Central Electricity Generating Board. Annual report and accounts 1974–75, page 11, 15.
2.
HeadlandH.Blaenau Ffestiniog and other medium-head pumped storage schemes in Great Britain. Proc. I. Mech. E.1961. vol. 175, no. 6, p. 319–366.
3.
GardnerG.C.HartA.B.MoffittR.D.WrightJ.K.Storing electrical energy on a large scale. CEGB Research, May 1975, no.2. pp.12–20.
4.
GlendenningI.Storing the energy of compressed air. CEGB Research, May 1975, no.2. pp.21–27.
5.
MeinersK.RomeykeN.SimonM.Air storage system for energy transfer — ASSET plant. 6th Conference on Thermodynamics and Fluid Mechanics, I.Mech.E., Durham, April 1976.
6.
High strength to weight alloys.Chartered Mechanical Engineer, May 1976, pp. 77–86.
7.
JonesG.BrislinR.T.Development program for the Fort St. Vrain Thermal Barrier. ASME paper 74-WA/HT-1.
8.
BaxiC.G.Del BeneJ.V.McKelveyT.E. Permeation flow and heat transfer in the HTGR thermal barrier. ASME paper 74-WA/HT-9.
9.
Comparative evaluation of Phase I results from the Energy Conversion Alternatives Study (ECAS) of ERDA/NSF. NASA TM x-71855, February 1976.
10.
CameP.M.The current state of research and design in high pressure ratio centrifugal compressors. NGTE Feb.1976. Lecture given at University of Newcastle Upon Tyne.
11.
Tables of thermal properties of gases. US Dept. of Commerce, National Bureau of Standards, Circular 564, Nov. 1955.
12.
ThorpeP.L.Enthalpy of air, oxygen, argon and nitrogen in the range 1–300 atma. British Oxygen Co., Oct. 1967. Entropy of air, oxygen, argon and nitrogen in the range 1–300 atma. British Oxygen Co., Jan. 1969.
13.
Private communication from B.A. Weldon, International Nickel Ltd., European Research and Development Centre:.
14.
Materials for cryogenic service-engineering properties. International Nickel, Sept. 1972.
15.
Mechanical and physical properties of the austenitic chromium-nickel stainless steels at sub-zero temperatures. International Nickel1966.
16.
Austenitic chromium-nickel stainless steels. Engineering properties at elevated temperatures. International Nickel1963 reprinted 1974.
KohlerJ.W.L.The gas refrigerating machine and its position in cryogenic technique. Progress in cryogenics, Vol.2, Ed. MendelssohnK., pp.43–67, Heywood & Co. Ltd., 1960.
24.
BrownA.DownW.S.Melting and freezing processes as a means of storing heat. I.Mech.E. Thermodynamics and Fluid Mechanics Conference, Durham, 1976, pp.1–7.
25.
SmithE.M.CoombsB.P.Thermal performance of cross-inclined tube bundles measured by a transient method. Journal of Mechanical Engineering Science, vol.14, no.3, 1972, pp. 205–220.
26.
SmithE.M.Research note: Heat transfer versus pumping power performance for cross-inclined tube banks. Journal of Mechanical Engineering Science, vol.15, no.5, 1973, pp.382–382.
27.
KingJ.L.SmithE.M. Unpublished work, University of Newcastle Upon Tyne.
28.
KernD. Q., ‘Process Heat Transfer’, McGraw Hill, 1950, pp. 664–670.
29.
FurnasC. C.‘Heat transfer from a gas stream to a bed of broken solids’. Trans Am. Inst. Chem. Engrs.193024, 142.
30.
ShepherdD. G.‘A low-pollution on-site, energy storage system for peak-power supply’ ASME Paper No. 74-GT-134, 1974.
31.
WeiermanC.TaborekJ.MarnerW. J.‘Comparison of the performance of in-line and staggered banks of tubes with segmented fins’. 15th National Heat Transfer Conference, San Francisco, Aug. 10–13, 1975, Am. Inst. Chem. Engrs. Paper No. 6.
32.
NASA Lewis Research Center, Comparative evaluation of Phase I results from the Energy Conversion Alternatives Study (ECAS). NASA TM X-71855, Feb. 1976.
33.
Westinghouse Electric Corporation Research Laboratories, ECAS Phase II Final Report. Vol. I: Combined gas-steam turbine plant with an integrated low-Btu gasifier. Vol. II: Combined gas-steam turbine plant using cool derived liquid fuel. Vol. III: Advanced steam plant with pressurised fluidised bed boilers. NASA CR: 134942, Nov. 1, 1976.
34.
General Electric Company Corporate Research and Development, ECAS Phase II Final Report. Vol. I: Executive summary. Vol. II: Part 1, analytical approach; Part 2, closed turbine cycles; Part 3, open cycle gas turbines and open cycle MHD; Part 4, summary of results. Vol. III: Research and development plans and implementation assessment. NASA CR 134949, December 1976.
35.
United Technologies Corporation, ECAS Phase II Final Report. Integrated coal gasifier/molten carbonate fuel cell powerplant. Conceptual design and implementation assessment. NASA CR 134955, 19 Oct. 1976.
36.
NASA Lewis Research Center, Evaluation of Phase II conceptual designs and implementation assessment resulting from the energy conversion alternatives study. NASA TM X-73515, April 1977.
37.
BrownA.DownW. S.‘Organic vapour heat recovery cycles with added mass’. 6th Thermodynamics and Fluid Mechanics Convention, Durham 6th-8th April 1976. Instn. Mech. Engrs., 1976–7, Paper C57/76, p 131.
38.
HarboeH.‘Power in 2000 AD — the case for pumped air storage’. ASEA International, Autumn 1971, pp 33–37.
39.
BackP.‘Hydroelectric power generation and pumped storage schemes utilising the sea’. Oceanology International ‘78 Conference Brighton 5th-10th March, 1978, Technical session L — energy from the sea.
40.
LiK. W.‘Compressed air-storage in gas turbine systems’. J. Engng. Pwr., Oct. 1975, 640–644.
41.
LiK. W.DuckwitzN. R.‘Cycle analysis of air-storage power plants’. ASME paper No. 76-GT-41.
42.
LiK. W.‘A second-law analysis of the air-storage gas turbine system’. ASME paper No. 76-JPGC-GT-2.
43.
PiersonO. L.‘Experimental investigation of the influence of tube arrangement on convection heat transfer and flow resistance in cross flow of gases over tube banks. Trans. Am. Soc. Mech. Engrs.1937, 563–572.